How WORKDAY works
Syntax
=WORKDAY(start_date, days, [holidays])start_date- The date you count from.
days- Business days to add. A negative number counts backwards.
holidays- Optional. A range of dates to skip.
Example
A report is due 3 business days before the date in C2.
=WORKDAY(C2, -3)Counts back three weekdays, so a Monday deadline gives the previous Wednesday.
Common mistakes
- Getting a number instead of a date. Format the cell as a date.
- Forgetting the holiday list around year end, so deadlines land on closed days.
Questions people ask
WORKDAY or NETWORKDAYS?
WORKDAY gives a date (start + business days). NETWORKDAYS gives a count (business days between two dates).