NETWORKDAYS: count working days

Lesson 36 of 54

NETWORKDAYS counts the weekdays (Monday to Friday) between two dates, including both, and can skip a list of holidays.

In cell D2, write a formula that counts the working days (Monday to Friday) from Start to End for Project A, including both dates. Fill down should work too.

D2
ABCD
1ProjectStartEndWorking days
2Project A3/2/20263/13/2026
3Project B3/9/20263/31/2026
4Project C4/1/20264/10/2026

Type in the formula bar above and press Enter to check.

Skip

How NETWORKDAYS works

Syntax

=NETWORKDAYS(start_date, end_date, [holidays])
start_date
The first day.
end_date
The last day. Both days are counted if they are weekdays.
holidays
Optional. A range of holiday dates to skip.

Example

You want the working days in a month, with company holidays listed in H2:H15.

=NETWORKDAYS(DATE(2026,12,1), DATE(2026,12,31), $H$2:$H$15)

The weekdays in December 2026 minus any holidays in the list.

Common mistakes

  • Expecting it to exclude the start day. NETWORKDAYS counts both ends; subtract 1 if you need the gap.
  • Holidays typed as text instead of real dates, so they aren't skipped.

Questions people ask

What if the weekend isn't Saturday and Sunday?

Use NETWORKDAYS.INTL, which lets you choose the weekend days.

Practice it above: type the formula in the formula bar and press Enter to check.